Milestone Inspections & Reserve Studies
Recent Florida legislation imposes new mandatory requirements for 1) the inspection of condominiums for structural integrity and 2) to conduct and fully fund a reserve study. Because these requirements are so important and onerous, the actual statute text is included in many instances.
The Botched Milestone Inspection Project
It is now widely understood that the Association botched the Milestone Inspection and Repair Project. This document will point out the project failures, why they occurred, and what should have been done differently.
Project Failures
- Because of inadequate communication, Association members will not know for 19 months past the date that the local enforcement agency (Jupiter Building Department) notified the Association to begin milestone inspections whether any building in Jupiter Bay has “substantial structural deterioration”.
- A large part of the $857,000 East C building concrete “repair” project was unnecessary, and it was unrelated to the Florida statutes requiring milestone inspections. Regardless, the Board, Property Manager and Attorney tried to convince unit owners that they were doing what was mandated.
- The Association wasted scarce engineering and construction resources on unnecessary work, whereas these resources could have been assigned to addressing units with more serious concrete damage and working on milestone inspections and the reserve study.
Why the Project Failed
- The Jupiter Bay Board failed to research and understand the new Florida statutes related to milestone inspections and Structural Integrity Reserve Studies (SIRSs). They either thought that they had all the answers or that the statutes were too complicated. Whereas all they needed to know is contained in two simple, easy to understand, Florida statutes: 718.112(2)(g) and 553.899, and building code 627.706.
- The Association received little or no guidance from the licensed Property Manager or Attorney. Both are supposed to know, understand, and advise the board regarding Florida condominium law. In fact, the Attorney sent letters to Jupiter Bay owners defending the Board’s flawed actions.
- The Board accepted the erroneous advice from a vendor (Engineering V-P) saying that “We consider the spalling located at the East C building to be substantial structural damage that needs to be fixed, including even spalls on minor units.” The new statutes specifically refute this.
What Should Have Been Done
Here are the eight steps presented in sequence (Their order is important):
- Soon after receiving the February 13, 2023, letter from the Town of Jupiter Building Department, the Association should have contracted with a licensed engineer or architect to begin milestone inspections of all Jupiter Bay buildings which are three stories or higher. According to the letter “A milestone inspection means a structural inspection of the building, including an inspection of the load-bearing walls and the primary structural members and primary structural systems as those terms are defined in section 627.706 of the Florida building code.”
- Within 14 days after receipt of the written notice from the local enforcement agency, the Association should have notified unit owners of the required milestone inspections and provided the date(s) when the milestone inspections would be completed.
- A phase one (initial) inspection of each building three stories or higher should have begun as soon as possible after receiving the Town’s letter, and a phase two (follow-up) inspection should have been done as necessary. A phase two of the milestone inspection must be performed if any substantial structural deterioration is identified during phase one. A phase two inspection may involve destructive or nondestructive testing at the inspector’s direction. If the architect or engineer finds no signs of substantial structural deterioration to any building components under visual examination, phase two of the inspection is not required.
- As requested in the Town’s letter, the Association needed to mail, upon completion of a phase one or phase two inspection of each building, a detailed inspection report, with a separate summary, to the Condominium Association and Jupiter Building Department. The summary must contain, at minimum, the material findings and recommendations.
- Within 45 days after receiving each inspection report, the Association should have distributed a copy of the inspector-prepared summary of the inspection report to each condominium unit owner, regardless of the findings or recommendations in the report, by United States mail or personal delivery, should have posted a copy of the inspector-prepared summary in a conspicuous place on the condominium property, and should have published the full report and inspector-prepared summary on the Association’s website.
- The Association should then have reviewed its findings with the Jupiter Building Department and obtained input regarding repair requirements based on any phase two inspection results. According to building code, an ordinance may be adopted requiring the Association to schedule or commence repairs for substantial structural deterioration within a specified timeframe after the Building Department receives a phase two inspection report; however, such repairs must be commenced within 365 days after receiving such report.
- The Association’s Board of Directors should then have reviewed findings and Building Department recommendations with unit owners to determine a course of action regarding any necessary building and unit repairs. At this time bids from construction firms are obtained (if required), and decisions are made at properly noticed Board Meetings as to which vendor(s) provides the best and most cost-effective solution. Costs and funding alternatives need to be discussed, and Board Members must vote and approve the vendor contract(s) and funding strategy.
- If the Board fails to submit proof to the local enforcement agency that repairs have been scheduled or have commenced for substantial structural deterioration identified in a phase two inspection report within the required timeframe, the local enforcement agency must review and determine if the building is unsafe for human occupancy.
Conclusions
Some corrections can still be made to salvage some of the project, but the Board must immediately do the following:
- Notify unit owners, and publish summaries, of the results of the milestone inspections to date.
- Stop “repair” work on the East C building that is unrelated to structural or major concrete damage. Divert construction resources to any required repairs in other buildings and units.
- Stop communicating that:
- Our “repairs’ in East C building are based on state mandated directives (which they are not).
- The spalling at East C is substantial structural damage (which it isn’t, and no milestone inspections were performed).
- We are ahead of the curve by locking up engineering and construction firms (assigning them to the wrong projects doesn’t help).
- We only addressed stacks in the West that had critical units because there was no state mandate in place when we began. (The new statutes would probably not have made any difference.)
- We can build reserves in advance to lessen owner impact. (There is no way without stretching the anticipated project over decades that $7.7 million can be accumulated in advance.)
- We are four months ahead of schedule in our milestone inspections. (No, the Board has five months to complete milestone inspections and SIRS without failing their fiduciary relationship to unit owners under Statute 718.111(1)(a).)
- Develop plans and schedules for any future building and unit inspections and repairs. Schedule a milestone inspection of the East C building. Notify unit owners of the SIRS progress.
- Publish clear rules and regulations regarding unit balcony repairs and upgrades. Define what is allowed, what owner alterations will be replaced and who will pay.
Structural Integrity Reserve Study Requirements
“Structural integrity reserve study” is defined as a study of the reserve funds required for future major repairs and replacement of the common elements based on a visual inspection of the common elements.
Condominium associations must have a structural integrity reserve study completed at least every 10 years after the condominium’s creation for each building on the condominium property that is three stories or higher in height. Associations existing on or before July 1, 2022, are to have a structural integrity reserve study completed by December 31, 2024.
The study is to include at a minimum, a study of the following items as related to the structural integrity and safety of the building:
-
- Roof.
- Structure, including load-bearing walls and other primary structural members and primary structural systems as those terms are defined in s. 627.706.
- Fireproofing and fire protection systems.
- Plumbing.
- Electrical systems.
- Waterproofing and exterior painting.
- Windows and exterior doors.
- Any other item that has a deferred maintenance expense or replacement cost over $10,000.
Structural Integrity Reserve Study Results
- The study is to:
- State the estimated remaining useful life of each identified item, and
- Provide the estimated replacement cost.
- The reserve study, performed by any qualified person or entity, may include other structural integrity inspections, besides visual inspections.
- Results of the reserve study must be included in the association’s annual reserve schedule.
- Results must be reflected in the association’s annual budget, starting in 2025, and quarterly maintenance assessment fees.
- Reserves must be fully funded, and association members are not permitted to vote to waive or partially fund the reserves.
- The Structural integrity reserve study needs to be kept in the official records for 15 years from the date of the report and posted on the association’s website.
- It is a breach of a board member or officer’s fiduciary duty if an association fails to complete a structural integrity reserve study. Furthermore, it could impact officer D&O insurance and property insurance premiums.
Reserve Schedule Development Process
Structural Integrity Reserve Study
718.112(2)(g) Structural integrity reserve study. The following is an abridged version of the actual statute language.
1. Items to be Inspected: A residential condominium association must have a structural integrity reserve study completed at least every 10 years after the condominium’s creation for each building on the condominium property that is three stories or higher in height, as determined by the Florida Building Code, which includes, at a minimum, a study of the following items as related to the structural integrity and safety of the building:
- Roof.
- Structure, including load-bearing walls and other primary structural members and primary structural systems as those terms are defined in s. 627.706.
- Fireproofing and fire protection systems.
- Plumbing.
- Electrical systems.
- Waterproofing and exterior painting.
- Windows and exterior doors.
- Any other item that has a deferred maintenance expense or replacement cost that exceeds $10,000 and the failure to replace or maintain such item negatively affects the items listed in sub-subparagraphs a.-g., as determined by the visual inspection portion of the structural integrity reserve study.
2. Inspector Qualifications: A structural integrity reserve study is based on a visual inspection of the condominium property. A structural integrity reserve study may be performed by any person qualified to perform such study. However, the visual inspection portion of the structural integrity reserve study must be performed or verified by an engineer licensed under chapter 471, an architect licensed under chapter 481, or a person certified as a reserve specialist or professional reserve analyst by the Community Associations Institute or the Association of Professional Reserve Analysts.
3. Reserve Study Results: At a minimum, a structural integrity reserve study must identify each item of the condominium property being visually inspected, state the estimated remaining useful life and the estimated replacement cost or deferred maintenance expense of each item of the condominium property being visually inspected, and provide a reserve funding schedule with a recommended annual reserve amount that achieves the estimated replacement cost or deferred maintenance expense of each item of condominium property being visually inspected by the end of the estimated remaining useful life of the item. The structural integrity reserve study may recommend that reserves do not need to be maintained for any item for which an estimate of useful life and an estimate of replacement cost cannot be determined, or the study may recommend a deferred maintenance expense amount for such item. The structural integrity reserve study may recommend that reserves for replacement costs do not need to be maintained for any item with an estimated remaining useful life of greater than 25 years, but the study may recommend a deferred maintenance expense amount for such item.
4. Applicability: Associations existing on or before July 1, 2022, must have a structural integrity reserve study completed by December 31, 2024, for each building on the condominium property that is three stories or higher in height.
5. Failure of Responsibility: If the officers or directors of an association willfully and knowingly fail to complete a structural integrity reserve study pursuant to this paragraph, such failure is a breach of an officer’s and director’s fiduciary relationship to the unit owners under s. 718.111(1).
Choosing the Right Engineering Firm for Inspections
Choosing the right engineering firm for Milestone Inspections is very important. The engineering firm must know:
- The difference between a Milestone Inspection (a structural inspection per FL Statutes 718.112(2)(h), 553.899 & 627.706) and a Concrete Restoration Inspection.
- The difference between a Phase 1 and Phase 2 Milestone Inspection, and that substantial structural deterioration requires a Phase 2 inspection before starting repairs.
- Their need to prepare a summary report of findings which is to be mailed to all condominium owners.
- That an engineer’s inspection report revealing “no severe damage” does not mean “substantial structural damage” when interpreted by another engineer.
- That “fixing minor spalls on units” is unnecessary and contrary to common sense. It is expensive, not required by FL statutes, and may prevent more serious spalling in other units from being addressed.
- According to a recent Webinar, 80% of the time engineering firms have certified buildings they inspect as “safe for occupancy with no substantial structural deterioration”, particularly when buildings are regularly painted and maintained.
Building Safety - FL Senate Bill 4-D
On May 26, 2022, Governor DeSantis signed into law Senate Bill 4-D, which passed during a 5-day special legislative session. This Bill is a response to the collapse last year of Champlain Towers South in Surfside FL and modifies Florida Statute Chapter 718.
The Bill establishes a statewide structural inspection program, requiring Condominium Associations to conduct Milestone Structural Inspections of their buildings, increases the rights of unit owners and prospective unit owners to access information regarding the condition of buildings, and revises requirements for associations to fund reserves for the continued maintenance and repair of their buildings.
Following is a summary of condominium association compliance requirements:
Building Safety Inspections
- Condominium association buildings that are three or more stories in height are required to have a “milestone inspection” of the buildings’ structural integrity by an architect or engineer when a building reaches:
-
- 30 years of age and every 10 years thereafter, or
- 25 years of age and every 10 years thereafter if the building is located within three miles of a coastline. (Jupiter Bay falls within this requirement.)
-
- If a milestone inspection is required and the building’s certificate of occupancy was issued on or before July 1, 1992, the building’s initial milestone inspection is to be performed before December 31, 2024. (Jupiter Bay’s buildings were built in the mid and late 80’s, and all meet this requirement.)
- Local enforcement agencies are required to notify associations of the need to perform a milestone inspection:
-
- A phase one milestone inspection by a licensed architect or engineer must commence within 180 days after an association receives a written notice from the agency, and
- A phase two inspection is required if there is evidence of “substantial structural deterioration”.
-
- Contents of the milestone inspection report, adhering to minimum requirements, are to be provided to local building officials with inspector-prepared summaries posted on association property and the association’s website, and provided to all unit owners by mail or email (if owner consents).
- The local enforcement agency is to review and determine if a building is safe for human occupancy if an association fails to submit proof that repairs for substantial deterioration have been scheduled or begun within at least 365 days after the local enforcement agency receives a phase two inspection report.
- Failure by an officer or director of an association to have a milestone inspection performed is a breach of the officer’s and director’s fiduciary relationship to the unit owners. Also, the association’s CAM or CAM firm contract must require compliance with these requirements.
- Unit owners have the right to inspect and copy, as official records, the milestone inspection report and all other inspection reports relating to structural or life safety, and renters have the right to inspect the milestone inspection reports.
- Associations are required to report to the FL Division of Condominiums, Timeshare, and Mobile Homes the number of buildings that are three stories or higher in height and the total number of units in such buildings on or before January 1, 2023. (Jupiter Bay has three 5-story buildings (containing 120 units) and six 4-story buildings (with 192 units)).
- Unit owners are required to give prospective buyers of a unit a copy of the inspector-prepared summary of the milestone inspection report.
Funding of Reserves:
- Condominium associations are required to complete a structural integrity reserve study every 10 years for each building in an association that is three stories or higher in height.
- Associations existing on or before July 1, 2022, are to have a structural integrity reserve study completed by December 31, 2024. (Jupiter Bay will need to schedule this and incorporate results in our 2025 budget or sooner.)
- “Structural integrity reserve study” is defined as a study of the reserve funds required for future major repairs and replacement of the common elements based on a visual inspection of the common elements.
- The study is to:
-
- Include a visual inspection by a licensed engineer or architect,
- State the estimated remaining useful life, and
- Provide the estimated replacement cost of the roof, load bearing walls or other primary structural members, floor, foundation, fireproofing and fire protection systems, plumbing, and any item with a deferred maintenance or replacement cost that exceeds $10,000.
-
- Besides visual inspections, any qualified person or entity may perform the other components of a structural integrity reserve study.
- Reserves must be fully funded, and association members are not permitted to vote to waive or partially fund the reserves.
- The Structural integrity reserve study needs to be kept in the official records for 15 years from the date of the report and posted on the association’s website.
- It is a breach of a board member or officer’s fiduciary duty if an association fails to complete a structural integrity reserve study. Furthermore, it could impact officer D&O insurance and property insurance premiums.
Milestone Inspection Due Dates
Condominium building Milestone Inspection requirements are based upon building age and the time from the prior Milestone Inspection.
Milestone Inspection Process
Additional detail can be found below in "Building Safety - FL Senate Bill 4-D".
Mandatory Milestone Inspections
718.112(2)(h) Mandatory milestone inspections.
- If an association is required to have a milestone inspection performed pursuant to s. 553.899, the association must arrange for the milestone inspection to be performed and is responsible for ensuring compliance with the requirements of s. 553.899.
- The association is responsible for all costs associated with the milestone inspection attributable to the portions of the building which the association is responsible for maintaining under the governing documents of the association.
- If the officers or directors of an association willfully and knowingly fail to have a milestone inspection performed pursuant to s. 553.899, such failure is a breach of the officers’ and directors’ fiduciary relationship to the unit owners under s. 718.111(1)(a).
- Within 14 days after receipt of a written notice from the local enforcement agency that a milestone inspection is required, the association must notify the unit owners of the required milestone inspection and provide the date by which the milestone inspection must be completed. Such notice may be given by electronic submission to unit owners who consent to receive notice by electronic submission or by posting on the association’s website.
- Within 45 days after receiving a phase one or phase two milestone inspection report from the architect or engineer who performed the inspection, the association must distribute a copy of the inspector-prepared summary of the inspection report to each unit owner, regardless of the findings or recommendations in the report, by United States mail or personal delivery at the mailing address, property address, or any other address of the owner provided to fulfill the association’s notice requirements under this chapter and by electronic transmission to the e-mail address or facsimile number provided to fulfill the association’s notice requirements to unit owners who previously consented to receive notice by electronic transmission; must post a copy of the inspector-prepared summary in a conspicuous place on the condominium property; and must publish the full report and inspector-prepared summary on the association’s website, if the association is required to have a website.
Florida Statute 553.899 - Structural Inspections
Title XXXIII REGULATION OF TRADE, COMMERCE, INVESTMENTS, AND SOLICITATIONS |
Chapter 553 BUILDING CONSTRUCTION STANDARDS |
553.899 Mandatory structural inspections for condominium and cooperative buildings.—
(1) The Legislature finds that maintaining the structural integrity of a building throughout the life of the building is of paramount importance in order to ensure that buildings are structurally sound so as to not pose a threat to the public health, safety, or welfare. As such, the Legislature finds that the imposition of a statewide structural inspection program for aging condominium and cooperative buildings in this state is necessary to ensure that such buildings are safe for continued use.
(2) As used in this section, the terms:
(a) “Milestone inspection” means a structural inspection of a building, including an inspection of load-bearing elements and the primary structural members and primary structural systems as those terms are defined in s. 627.706, by an architect licensed under chapter 481 or engineer licensed under chapter 471 authorized to practice in this state for the purposes of attesting to the life safety and adequacy of the structural components of the building and, to the extent reasonably possible, determining the general structural condition of the building as it affects the safety of such building, including a determination of any necessary maintenance, repair, or replacement of any structural component of the building. The purpose of such inspection is not to determine if the condition of an existing building is in compliance with the Florida Building Code or the firesafety code. The milestone inspection services may be provided by a team of professionals with an architect or engineer acting as a registered design professional in responsible charge with all work and reports signed and sealed by the appropriate qualified team member.
(b) “Substantial structural deterioration” means substantial structural distress or substantial structural weakness that negatively affects a building’s general structural condition and integrity. The term does not include surface imperfections such as cracks, distortion, sagging, deflections, misalignment, signs of leakage, or peeling of finishes unless the licensed engineer or architect performing the phase one or phase two inspection determines that such surface imperfections are a sign of substantial structural deterioration.
(3) Requirements:
(a) An owner or owners of a building that is three stories or more in height as determined by the Florida Building Code and that is a residential condominium under chapter 718 must have a milestone inspection performed by December 31 of the year in which the building reaches 30 years of age, based on the date the certificate of occupancy for the building was issued, and every 10 years thereafter. If a building reached 30 years of age before July 1, 2022, the building’s initial milestone inspection must be performed before December 31, 2024. If a building reaches 30 years of age on or after July 1, 2022, and before December 31, 2024, the building’s initial milestone inspection must be performed before December 31, 2025. If the date of issuance for the certificate of occupancy is not available, the date of issuance of the building’s certificate of occupancy shall be the date of occupancy evidenced in any record of the local building official.
(b) The local enforcement agency may determine that local circumstances, including environmental conditions such as proximity to salt water as defined in s. 379.101, require that a milestone inspection must be performed by December 31 of the year in which the building reaches 25 years of age, based on the date the certificate of occupancy for the building was issued, and every 10 years thereafter.
(c) The local enforcement agency may extend the date by which a building’s initial milestone inspection must be completed upon a showing of good cause by the owner or owners of the building that the inspection cannot be timely completed if the owner or owners have entered into a contract with an architect or engineer to perform the milestone inspection and the inspection cannot reasonably be completed before the deadline or other circumstance to justify an extension.
(d) The local enforcement agency may accept an inspection report prepared by a licensed engineer or architect for a structural integrity and condition inspection of a building performed before July 1, 2022, if the inspection and report substantially comply with the requirements of this section. Notwithstanding when such inspection was completed, the condominium or cooperative association must comply with the unit owner notice requirements in subsection (9). The inspection for which an inspection report is accepted by the local enforcement agency under this paragraph is deemed a milestone inspection for the applicable requirements in chapters 718 and 719. If a previous inspection and report is accepted by the local enforcement agency under this paragraph, the deadline for the building’s subsequent 10-year milestone inspection is based on the date of the accepted previous inspection.
(4) The milestone inspection report must be arranged by the condominium association. The association is responsible for ensuring compliance with the requirements of this section and is responsible for all costs associated with the milestone inspection. This section does not apply to a single-family, two-family, or three-family dwelling with three or fewer habitable stories above ground.
(5) Upon determining that a building must have a milestone inspection, the local enforcement agency must provide written notice of such required inspection to the condominium association by certified mail, return receipt requested. The condominium association must notify the unit owners of the required milestone inspection within 14 days after receipt of the written notice from the local enforcement agency and provide the date that the milestone inspection must be completed. Such notice may be given by electronic submission to unit owners who consent to receive notice by electronic submission or by posting on the association’s website.
(6) Phase one of the milestone inspection must be completed within 180 days after the owner or owners of the building receive the written notice under subsection (5). For purposes of this section, completion of phase one of the milestone inspection means the licensed engineer or architect who performed the phase one inspection submitted the inspection report by e-mail, United States Postal Service, or commercial delivery service to the local enforcement agency.
(7) A milestone inspection consists of two phases:
(a) For phase one of the milestone inspection, a licensed architect or engineer authorized to practice in this state shall perform a visual examination of habitable and nonhabitable areas of a building, including the major structural components of a building, and provide a qualitative assessment of the structural conditions of the building. If the architect or engineer finds no signs of substantial structural deterioration to any building components under visual examination, phase two of the inspection, as provided in paragraph (b), is not required. An architect or engineer who completes a phase one milestone inspection shall prepare and submit an inspection report pursuant to subsection (8).
(b) A phase two of the milestone inspection must be performed if any substantial structural deterioration is identified during phase one. A phase two inspection may involve destructive or nondestructive testing at the inspector’s direction. The inspection may be as extensive or as limited as necessary to fully assess areas of structural distress in order to confirm that the building is structurally sound and safe for its intended use and to recommend a program for fully assessing and repairing distressed and damaged portions of the building. When determining testing locations, the inspector must give preference to locations that are the least disruptive and most easily repairable while still being representative of the structure. If a phase two inspection is required, within 180 days after submitting a phase one inspection report the architect or engineer performing the phase two inspection must submit a phase two progress report to the local enforcement agency with a timeline for completion of the phase two inspection. An inspector who completes a phase two milestone inspection shall prepare and submit an inspection report pursuant to subsection (8).
(8) Upon completion of a phase one or phase two milestone inspection, the architect or engineer who performed the inspection must submit a sealed copy of the inspection report with a separate summary of, at minimum, the material findings and recommendations in the inspection report to the condominium association and to the building official of the local government which has jurisdiction. The inspection report must, at a minimum, meet all of the following criteria:
(a) Bear the seal and signature, or the electronic signature, of the licensed engineer or architect who performed the inspection.
(b) Indicate the manner and type of inspection forming the basis for the inspection report.
(c) Identify any substantial structural deterioration, within a reasonable professional probability based on the scope of the inspection, describe the extent of such deterioration, and identify any recommended repairs for such deterioration.
(d) State whether unsafe or dangerous conditions, as those terms are defined in the Florida Building Code, were observed.
(e) Recommend any remedial or preventive repair for any items that are damaged but are not substantial structural deterioration.
(f) Identify and describe any items requiring further inspection.
(9) Within 45 days after receiving the applicable inspection report, the condominium association must distribute a copy of the inspector-prepared summary of the inspection report to each condominium unit owner, regardless of the findings or recommendations in the report, by United States mail or personal delivery at the mailing address, property address, or any other address of the owner provided to fulfill the association’s notice requirements under chapter 718 or chapter 719, as applicable, and by electronic transmission to the e-mail address or facsimile number provided to fulfill the association’s notice requirements to unit owners who previously consented to receive notice by electronic transmission; must post a copy of the inspector-prepared summary in a conspicuous place on the condominium or cooperative property; and must publish the full report and inspector-prepared summary on the association’s website, if the association is required to have a website.
(10) A local enforcement agency may prescribe timelines and penalties with respect to compliance with this section.
(11) A board of county commissioners or municipal governing body may adopt an ordinance requiring that a condominium association schedule or commence repairs for substantial structural deterioration within a specified timeframe after the local enforcement agency receives a phase two inspection report; however, such repairs must be commenced within 365 days after receiving such report. If an owner of the building fails to submit proof to the local enforcement agency that repairs have been scheduled or have commenced for substantial structural deterioration identified in a phase two inspection report within the required timeframe, the local enforcement agency must review and determine if the building is unsafe for human occupancy.
(12) By December 31, 2024, the Florida Building Commission shall adopt rules pursuant to ss. 120.536(1) and 120.54 to establish a building safety program for the implementation of this section within the Florida Building Code: Existing Building. The building inspection program must, at minimum, include inspection criteria, testing protocols, standardized inspection and reporting forms that are adaptable to an electronic format, and record maintenance requirements for the local authority.
(13) The Florida Building Commission shall consult with the State Fire Marshal to provide recommendations to the Legislature for the adoption of comprehensive structural and life safety standards for maintaining and inspecting all types of buildings and structures in this state that are three stories or more in height. The commission shall provide a written report of its recommendations to the Governor, the President of the Senate, and the Speaker of the House of Representatives by December 31, 2023.
Milestone Inspection Report
- Bears the seal and signature, or the electronic signature, of the licensed engineer or architect who performed the inspection.
- Indicates the manner and type of inspection forming the basis for the inspection report.
- Identifies any substantial structural deterioration, within a reasonable professional probability based on the scope of the inspection, describes the extent of such deterioration, and identifies any recommended repairs for such deterioration.
- States whether unsafe or dangerous conditions, as those terms are defined in the Florida Building Code, were observed.
- Recommends any remedial or preventive repair for any items that are damaged but are not substantial structural deterioration.
- Identifies and describes any items requiring further inspection.
Florida Statute 627.706 - Primary Structural Systems
|
|||
627.706 Sinkhole insurance; catastrophic ground cover collapse; definitions.—
(2)(k) “Structural damage” means a covered building, regardless of the date of its construction, has experienced the following: 1. Interior floor displacement or deflection in excess of acceptable variances as defined in ACI 117-90 or the Florida Building Code, which results in settlement-related damage to the interior such that the interior building structure or members become unfit for service or represents a safety hazard as defined within the Florida Building Code; 2. Foundation displacement or deflection in excess of acceptable variances as defined in ACI 318-95 or the Florida Building Code, which results in settlement-related damage to the primary structural members or primary structural systems that prevents those members or systems from supporting the loads and forces they were designed to support to the extent that stresses in those primary structural members or primary structural systems exceeds one and one-third the nominal strength allowed under the Florida Building Code for new buildings of similar structure, purpose, or location; 3. Damage that results in listing, leaning, or buckling of the exterior load-bearing walls or other vertical primary structural members to such an extent that a plumb line passing through the center of gravity does not fall inside the middle one-third of the base as defined within the Florida Building Code; 4. Damage that results in the building, or any portion of the building containing primary structural members or primary structural systems, being significantly likely to imminently collapse because of the movement or instability of the ground within the influence zone of the supporting ground within the sheer plane necessary for the purpose of supporting such building as defined within the Florida Building Code; or 5. Damage occurring on or after October 15, 2005, that qualifies as “substantial structural damage” as defined in the Florida Building Code. |
Unit Sale Disclosure
A contract that does not conform to the requirements of this paragraph is voidable at the option of the purchaser prior to closing.
718.503(2) NONDEVELOPER DISCLOSURE. The following is an abridged version of the actual statute language.
(a) Each unit owner must comply with this subsection before the sale of his or her unit. Each prospective purchaser who has entered into a contract for the purchase of a condominium unit is entitled, at the seller’s expense, to a current copy of the following additional documents:
- A copy of the inspector-prepared summary of the milestone inspection report as described in s. 553.899, if applicable.
- The association’s most recent structural integrity reserve study or a statement that the association has not completed a structural integrity reserve study.
A contract that does not conform to the requirements of the following paragraph is voidable at the option of the purchaser prior to closing:
(e) Case #1 – Inspection & SIRS Required but Not Completed. If the association is required to have completed a milestone inspection as described in s. 553.899 or a structural integrity reserve study, and the association has not completed the milestone inspection, or the structural integrity reserve study, each contract entered into after December 31, 2024, for the sale of a residential unit shall contain in conspicuous type a statement indicating that the association is required to have a milestone inspection or a structural integrity reserve study and has not completed such inspection, report, or study, as appropriate.
Case #2 – Inspection or SIRS Not Required. If the association is not required to have a milestone inspection as described in s. 553.899 or a structural integrity reserve study, each contract entered into after December 31, 2024, for the sale of a residential unit shall contain in conspicuous type a statement indicating that the association is not required to have a milestone inspection or a structural integrity reserve study, as appropriate.
Case #3 – Inspection & SIRS Completed. If the association has completed a milestone inspection as described in s. 553.899, a turnover inspection report for a turnover inspection performed on or after July 1, 2023, or a structural integrity reserve study, each contract entered into after December 31, 2024, for the resale of a residential unit shall contain in conspicuous type:
1. A clause which states: THE BUYER HEREBY ACKNOWLEDGES THAT BUYER HAS BEEN PROVIDED A CURRENT COPY OF THE INSPECTOR-PREPARED SUMMARY OF THE MILESTONE INSPECTION REPORT AS DESCRIBED IN SECTION 553.899, FLORIDA STATUTES, IF APPLICABLE; AND A COPY OF THE ASSOCIATION’S MOST RECENT STRUCTURAL INTEGRITY RESERVE STUDY DESCRIBED IN SECTIONS 718.103(26) AND 718.112(2)(g), FLORIDA STATUTES, IF APPLICABLE, MORE THAN 3 DAYS, EXCLUDING SATURDAYS, SUNDAYS, AND LEGAL HOLIDAYS, PRIOR TO EXECUTION OF THIS CONTRACT; and
2. A clause which states: THIS AGREEMENT IS VOIDABLE BY BUYER BY DELIVERING WRITTEN NOTICE OF THE BUYER’S INTENTION TO CANCEL WITHIN 3 DAYS, EXCLUDING SATURDAYS, SUNDAYS, AND LEGAL HOLIDAYS, AFTER THE DATE OF EXECUTION OF THIS AGREEMENT BY THE BUYER AND RECEIPT BY BUYER OF A CURRENT COPY OF THE INSPECTOR-PREPARED SUMMARY OF THE MILESTONE INSPECTION REPORT AS DESCRIBED IN SECTION 553.899, FLORIDA STATUTES, IF APPLICABLE; AND A COPY OF THE ASSOCIATION’S MOST RECENT STRUCTURAL INTEGRITY RESERVE STUDY DESCRIBED IN SECTIONS 718.103(26) AND 718.112(2)(g), FLORIDA STATUTES, IF APPLICABLE. ANY PURPORTED WAIVER OF THESE VOIDABILITY RIGHTS SHALL BE OF NO EFFECT. BUYER MAY EXTEND THE TIME FOR CLOSING FOR A PERIOD OF NOT MORE THAN 3 DAYS, EXCLUDING SATURDAYS, SUNDAYS, AND LEGAL HOLIDAYS, AFTER THE BUYER RECEIVES A CURRENT COPY OF THE INSPECTOR-PREPARED SUMMARY OF THE MILESTONE INSPECTION REPORT AS DESCRIBED IN SECTION 553.899, FLORIDA STATUTES; OR A COPY OF THE ASSOCIATION’S MOST RECENT STRUCTURAL INTEGRITY RESERVE STUDY DESCRIBED IN SECTIONS 718.103(26) AND 718.112(2)(g), FLORIDA STATUTES, IF REQUESTED IN WRITING. BUYER’S RIGHT TO VOID THIS AGREEMENT SHALL TERMINATE AT CLOSING.